PMP Exam Set A – Q98 ( PMBOK 6th edition )

Jane has recently finalized her project management plan and has also got it approved. She is managing a complex manufacturing process improvement project. The project stakeholders’ continuous support and commitment is an absolute must for the success of the project. Which of the following are the most crucial stakeholder management processes at this stage?

A. Plan Stakeholder Engagement and Manage Stakeholder Engagement
B. Identify Stakeholders and Plan Stakeholder Engagement
C. Manage Stakeholder Engagement and Monitor Stakeholder Engagement
D. Plan Stakeholder Engagement and Monitor Stakeholder Engagement

C. Manage Stakeholder Engagement and Monitor Stakeholder Engagement