PMP Exam Set B – Q60

A project manager colleague of yours is currently working under contract on a short term project. He has expressed some concerns about finding work after the project ends. The project he is working on is currently ahead of schedule and he expects they will finish a month sooner than initially expected. What advice would be appropriate to provide him?

A. Slow down work on the project to have it finish on schedule.
B. Continue the work within the project’s scope and possibly finish ahead of schedule.
C. Exaggerate his experience to the sponsor to try to get a project manager position for him on other upcoming projects.
D. Inform the client the project is behind schedule and it will have to be extended.

B. Continue the work within the project’s scope and possibly finish ahead of schedule.

PMP Exam Set A – Q13

You are managing a highly complex drug manufacturing project and your sponsor is highly motivated and influential. You are optimistic about the outcome of the project, however, you are not sure about the project approval requirements that measure the success of the project. So, you would like to document the name of the person who signs off on the project, and the criteria that constitutes the success of the project. Which of the following documents should you use first to incorporate project approval requirements?

A. The scope document
B. The project charter
C. The approval requirement plan
D. The project management plan

B. The project charter