PMP Exam Set B – Q80

Which of the following structures is helpful in tracking project costs and can be aligned with the organization’s accounting system?

A. Project breakdown structure (PBS)
B. Matrix breakdown structure (MBS)
C. Work Breakdown Structure (WBS)
D. Organizational breakdown structure (OBS)

C. Work Breakdown Structure (WBS)