PMP Exam Set B – Q80

Which of the following structures is helpful in tracking project costs and can be aligned with the organization’s accounting system?

A. Project breakdown structure (PBS)
B. Matrix breakdown structure (MBS)
C. Work Breakdown Structure (WBS)
D. Organizational breakdown structure (OBS)

C. Work Breakdown Structure (WBS)
Tagged with 
Matrix breakdown structure (MBS) Project breakdown structure (PBS) Project Cost Management
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2025 Premium PMP Exam Questions
×Close