John’s project is in execution. During the monitoring and controlling of the project, John finds out that the current stakeholder engagement strategy needs to be thoroughly reviewed. He invites selected key stakeholders and some subject matter experts to brainstorm on new ideas and approaches that can be used. John is planning to facilitate the session himself. The planed session in this scenario is an example of?
A. Project status update meeting
B. Integrated change control
C. Project quality control
D. Expert judgment obtained through a focus group