A project uses rounding of activity estimates data to the nearest $100, uses staff hours as the unit of measure for resources, and has a variance threshold of 10% deviation from the baseline plan. These would be typically documented in the:
A. Cost management plan
B. Scope Statement
C. WBS
D. Project charter