Accepted deliverables are an input to the Close Project or Phase process. These deliverables would have been accepted through which of the following processes?
A. Validate Scope
B. Control Quality
C. Control Scope
D. Manage Quality
Accepted deliverables are an input to the Close Project or Phase process. These deliverables would have been accepted through which of the following processes?
A. Validate Scope
B. Control Quality
C. Control Scope
D. Manage Quality