Accepted deliverables are an input to the Close Project or Phase process. These deliverables would have been accepted through which of the following processes?
A. Validate Scope
B. Control Quality
C. Control Scope
D. Manage Quality
Accepted deliverables are an input to the Close Project or Phase process. These deliverables would have been accepted through which of the following processes?
A. Validate Scope
B. Control Quality
C. Control Scope
D. Manage Quality
A fellow project manager is retiring and moving to the mountains, you will be taking over his project. Before he leaves he tells you the project is on schedule, but only because he has had to “put the hammer down” on his project team and push them relentlessly. Pushing the team to perform activities to accomplish project objectives is a part of:
A. Direct and Manage Project Work
B. Monitor and Control Project Work
C. Control Quality
D. Control Scope