PMP Exam Set C – Q94

You are the Project Manager for Motor Cars, Corp. You are working on a project for the Human Resources department that is scheduled to take one year. After three months into the project, you calculate the EV at $35,000 and the PV at $45,000. Which option below represents the value for the SV?

A. -$10,000
B. 1.29
C. 0.78
D. $10,000

A. -$10,000