Project performance measurements are used to assess the magnitude of variation from the original scope baseline. Once the degree of scope variation is known, what step is performed next?
A. Audit the project team
B. Upgrade the configuration management database with new controls.
C. Replanning
D. Root cause analysis of the cause of the variance relative to the scope baseline.