PMP Exam Set D – Q85

Which of the following is not an example of parametric estimating?

A. Activity duration estimated based on the number of drawings multiplied by the number of labor hours per drawing.
B. Activity duration estimated based on the number of labor hours per meter for cable installation.
C. Activity duration estimated based on the square footage in construction.
D. Activity duration estimated based on the actual duration of a similar, previous project.

D. Activity duration estimated based on the actual duration of a similar, previous project.