PMP Exam Set G – Q43

All of the following activities are performed in the Close Project or Phase process EXCEPT

A. Activities that fulfill the exit criteria of the project
B. Sending the deliverables to the customer for acceptance
C. Activities which are needed to transfer the completed products to operations
D. Documenting the reasons for projects terminated early

B. Sending the deliverables to the customer for acceptance

PMP Exam Set F – Q12

You are working with your customers on completed deliverables in your electronic parts manufacturing project. Since these parts are exported to other countries, they need more testing before your customers accept them. In this scenario, which of the following statements about the completed deliverables is CORRECT?

A. Completed deliverables not accepted by customers must be forwarded to the close project or phase process
B. Deliverables formally accepted by customers must be moved to organizational process assets
C. Deliverables formally accepted by customers are forwarded to the validate scope process
D. Completed deliverables not accepted by customers must require a change request for defect repair

D. Completed deliverables not accepted by customers must require a change request for defect repair