You have your project team members record the time they spend on different activities during the day such as: programming, electrical, HVAC, etc. This is an example of a tool and technique in what process?

A. Manage Communications
B. Direct and Manage Project Work
C. Monitor and Control Project Work
D. Manage Team

C. Monitor and Control Project Work