Peter’s project is in execution. Peter has a monthly stakeholder update meeting set up where he presents the project’s progress and current issues to the key stakeholders. During the last stakeholder update meeting, the stakeholders requested Peter to provide bi-weekly project updates instead of monthly updates. The communication management plan has been broadly framed and it doesn’t restrict Peter from doing bi-weekly updates. What should Peter do?
A. Start providing bi-weekly updates instead of monthly updates.
B. Update the communication management plan prior to providing the bi-weekly updates.
C. Disregard the stakeholders’ request and continue with the monthly updates.
D. Request the stakeholders to submit a change request.