PMP Exam Set E – Q84

Jane is managing a complex multimillion dollar project. The number of the project stakeholders is high and most of the project stakeholders are heavily interested in the project. Providing daily project updates to the project stakeholders is becoming difficult for Jane because of the effort required to prepare and distribute this information. In this situation, which of the following can help Jane prepare and distribute the project information?

A. Configuration management system
B. Information management system
C. Change control system
D. Quality management system

B. Information management system