PMP Exam Set C – Q3

Which of these precedence relationships is most commonly used in Precedence Diagramming Method?

A. Finish to Start
B. Start to Finish
C. Start to Start
D. Finish to Finish

A. Finish to Start
Tagged with 
Finish to Finish Finish to Start Precedence Diagramming Method Project Schedule Management Start to Finish Start to Start
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2025 Premium PMP Exam Questions
×Close