A project manager has been asked to manage a research project. By its very nature, this type of project is not very clearly defined and involves a lot of uncertainty. What phase-to-phase relationship should the project manager use for this project?
A. Open-ended relationship
B. Overlapping relationship
C. Iterative relationship
D. Sequential relationship