Due to unforeseen circumstances your supplier has run out of the cement needed for your construction project. What is the BEST strategy for dealing with this issue?
A. Implement a workaround
B. Implement the contingency response strategy
C. Refer to the risk register
D. Refer to probability and impact matrix