PMP Exam Set B – Q97

Debbie, an IT project manager, is in the planning phase of a shopping website development project. A junior project manager, who has been working under her authority, started developing procedures to indicate how the integrity of cost and schedule performance baselines should be maintained in the project. Where should the junior project manager store these procedures?

A. In the project human resource plan
B. In the project scope statement
C. In the project management plan
D. In the project communication plan

C. In the project management plan