PMP Exam Set E – Q11 ( PMBOK 6th edition )

Identification of new risks, reassessment of old risks and closing of outdated risks are done as part of the Monitor Risks process. How often should project risk reassessment be scheduled?

A. It depends on how the project progresses relative to its objectives.
B. It is left to the discretion of the project manager.
C. Reassessment needs to be done at the 25%, 50%, and 75% stages of project completion.
D. Reassessment needs to be done at the 20%, 40%, 60% and 80% stages of project completion.

A. It depends on how the project progresses relative to its objectives.