PMP Exam Set E – Q2 ( PMBOK 6th edition )

Which of the Project Schedule Management processes involves identifying and documenting dependencies between schedule activities?

A. Sequence Activities
B. Define Activities
C. Develop Schedule
D. Control Schedule

A. Sequence Activities
Tagged with 
Project Schedule Management processes
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2023 Premium PMP Exam Questions
×Close