PMP Exam Set C – Q51

Which of the following items needs to be kept in mind when relying on risk identification checklists?

A. They are biased.
B. They are not exhaustive.
C. They are often inaccurate.
D. They are easy to prepare.

B. They are not exhaustive.
Tagged with 
Project Risk Management risk identification checklists
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2023 Premium PMP Exam Questions
×Close