As part of your staffing management plan, you have developed a chart indicating the # of hours (Y axis) a senior programmer will be working over the months (X axis) of the project. This is an example of what?
A. Pareto Chart
B. Ishikawa Diagram
C. Resource Histogram
D. Staff Acquisition Chart