PMP Exam Set D – Q9

Teams go through various stages of development. As per the Tuckman ladder of development, the stage during which the least amount of work gets done is usually the:

A. Storming phase
B. Forming phase
C. Norming phase
D. Performing phase

B. Forming phase
Tagged with 
Forming phase Norming phase Performing phase Storming phase Tuckman ladder
 

PMP Exam Set B – Q1

Your project team members have just started to work together and are now adjusting their work habits and behaviors to support each other. Which stage of the Tuckman ladder has your team just entered?

A. Norming
B. Performing
C. Forming
D. Storming

A. Norming
Tagged with 
Forming Norming Performing Project Human Resource Management Storming Tuckman ladder work habits and behaviors
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2025 Premium PMP Exam Questions
×Close