PMP Exam Set F – Q52

You are fairly new to project management, but have been successfully managing a small project and now management has given you another project to manage, which you are excited about. However, the new project is growing exponentially everyday, you have also learned a project manager you work with managed a similar project last year. What

PMP Exam Set F – Q51

A project manager is looking at various classification methods to share information among project stakeholders. Which of the following correctly classifies the different methods used? A. Pull communication – Meetings; Push communication – Newsletters; Interactive communication – E-learning repositoryB. Interactive communication – Meetings; Push communication – E-learning repository; Pull communication – NewslettersC. Push communication –

PMP Exam Set F – Q50

Emily’s project has got a huge number of key positive and negative stakeholders. It is very important to closely manage the influential negative stakeholders to ensure project’s success. Do the key positive stakeholders need to be managed as well? A. No; more attention needs to be given to the key negative stakeholders.B. The positive stakeholders

PMP Exam Set F – Q49

When are risk identification activities performed? A. During the Perform Qualitative Risk Analysis processB. During the Plan Risk Management processC. During the Perform Quantitative Risk Analysis processD. Ongoing throughout the project Show Answer D. Ongoing throughout the project

PMP Exam Set F – Q48

One of the senior team members, who is the best performer in your project plays ‘favorites’ and a few of the team members who work closely with him, have got very good appraisal reports in the past, even though they may not have deserved it. As the project manager, what would you need to proactively

PMP Exam Set F – Q47

Peter wants to assign a risk owner for every project risk for which a risk response action has been planned. Where must he update this information? A. Human resource management planB. Risk registerC. Stakeholder registerD. Project charter Show Answer B. Risk register

PMP Exam Set F – Q46

Jane works as a project manager for the National weather agency. She has been managing a project which was designed to find the impact of climate changes on Northern mountains. The initial study established two months delay for the testing equipment to reach mountains due to road construction. However, a recent assessment has shown a

PMP Exam Set F – Q45

You are a project manager for your company. Part of the project requires producing 10,000 widgets, which your company will outsource. The company has agreed to pay all related costs and 5% of the estimated project costs. What type of contract has been negotiated? A. Cost-Plus-Incentive-Fee contractB. Cost-Plus-Fixed-Fee contractC. Time and Material contractD. Fixed-price contract

PMP Exam Set F – Q44

Activity attributes extend the description of the activity by identifying various components associated with the activity. Typically how many attributes are associated with each activity? A. They should be between 5 and 10 in numberB. The number of attributes varies by application area.C. They should be less than 5 in numberD. The number of attributes

PMP Exam Set F – Q43

Control Schedule is part of which Project Management process group? A. Monitoring and controllingB. PlanningC. ExecutingD. Initiating Show Answer A. Monitoring and controlling