PMP Exam Set F – Q61

Which of the following is accurate regarding the Estimate Activity Resources process? A. It produces project resource calendars as the outputB. It determines dependencies that may require a lead or lag to define the relationshipC. This process is coordinated independent of the Estimate Cost processD. It involves determining what and how many resources will be

PMP Exam Set F – Q60

The Make-or-Buy analysis is a technique that is used as part of the Plan Procurement Management process. It is used to determine whether a particular product or service can be produced by the project team or should it be purchased. The analysis to arrive at a decision should include: A. Indirect costs onlyB. Direct as

PMP Exam Set F – Q59

A project manager has been asked to manage a research project. By its very nature, this type of project is not very clearly defined and involves a lot of uncertainty. What phase-to-phase relationship should the project manager use for this project? A. Open-ended relationshipB. Overlapping relationshipC. Iterative relationshipD. Sequential relationship Show Answer C. Iterative relationship

PMP Exam Set F – Q58

A seller started out a project on the basis of a Time and Material contract. The initial contract amount based on the agreed-upon rates and effort was $ 100,000 over a 1 year period. However, when the project was completed, the total contract value turned out to be $ 350,000 over a 2 year period.

PMP Exam Set F – Q56

What is the best way to show, at a glance, all the work packages or project activities assigned to a specific organizational department? A. Organizational Breakdown StructureB. RACI chartC. Work Breakdown StructureD. Roles and Responsibilities Chart Show Answer A. Organizational Breakdown Structure

PMP Exam Set F – Q55

A project manager used the services of a trained moderator during the Collect Requirements process. Which of the following is likely to have required the services of a trained moderator? A. InterviewsB. PrototypesC. QuestionnairesD. Focus groups Show Answer D. Focus groups

PMP Exam Set F – Q54

Organizations evaluate the need of buying products versus making the items themselves. Which of the following is not a factor that influences the make-or-buy decisions: A. Core capabilities of the organizationB. Value delivered by vendors meeting the needC. Total duration of the projectD. Risk associated with meeting the need in a cost-effective manner Show Answer

PMP Exam Set F – Q53

Risks may be identified during the entire lifecycle of a project. Identify Risks is what type of process? A. QualitativeB. Effort drivenC. DiscreteD. Iterative Show Answer D. Iterative