You are the project manager from a seller organization, based at the customer location. One of your team members is involved in certain unacceptable activities at the customer location. The HR manager of the customer team organizes a meeting between you, the team-member, your customer- manager and HR wherein the team member apologizes for his
PMP Exam Set D – Q41
You have a schedule activity that can be delayed without delaying the early start date of any subsequent activities. This is an example of? A. Free FloatB. Lead FloatC. Total FloatD. Lag Float Show Answer A. Free Float
PMP Exam Set D – Q40
The term ____________ indicates the degree to which a particular product or service meets requirements, while ____________ indicates a category or rank used to distinguish that item from other similar items. A. Quality, gradeB. Grade, standardC. Grade, qualityD. Quality, standard Show Answer A. Quality, grade
PMP Exam Set D – Q39
A project to design and build a new aircraft is cancelled after the project has been underway for some time. What process is invoked to document what work was done, and to what extent it was completed? A. Manage ScopeB. Close ScopeC. Perform Quality ControlD. Close Project or Phase Show Answer D. Close Project or
PMP Exam Set D – Q38
As part of your staffing management plan, you have developed a chart indicating the # of hours (Y axis) a senior programmer will be working over the months (X axis) of the project. This is an example of what? A. Pareto ChartB. Ishikawa DiagramC. Resource HistogramD. Staff Acquisition Chart Show Answer C. Resource Histogram
PMP Exam Set D – Q37
During the execution of your project, you decide that you would like to have charts of your project status – cost and schedule, display certain key project data, and hold your project meetings in a specific conference room. Such a place would be called: A. ArmageddonB. War roomC. BattlefieldD. Ground zero Show Answer B. War
PMP Exam Set D – Q36
The project you are working on has received an invoice from a vendor for USD $17,500. However, your team believes the correct total due is $15,300. When you notify the vendor of this, the vendor still insists on US$ 17,500. What is the best course of action now? A. Pay $15,300.B. Negotiate with the vendor.C.
PMP Exam Set D – Q35
A project is contracted as a Cost-Plus-Incentive-Fee (CPIF) type of contract. The project is negotiated such that if the final costs are less than expected costs, the sharing formula for cost savings is 80:20. The targeted cost is US$ 500,000 with a 10% fee. If the project comes in at US$ 450,000, what would be
PMP Exam Set D – Q34
The Quality Policy is the intended direction of a performing organization with regard to quality. As a project manager in a performing organization, you find that the organization lacks a formal quality policy. What should be done in such a case? A. The project management team need not develop a quality policy since the performing
PMP Exam Set D – Q33
Which of the following statements is correct? A. A collection of unrelated programs can constitute a portfolio.B. The scope of a portfolio is typically smaller than that of a program.C. A program is a group of unrelated projects.D. A program need not consist of projects. Show Answer A. A collection of unrelated programs can constitute