As you are creating the Activity List, which technique is recommended for subdividing the project into smaller components called activities?
A. Decomposition
B. Rolling Wave Planning
C. Expert judgment
D. Deconstruction
As you are creating the Activity List, which technique is recommended for subdividing the project into smaller components called activities?
A. Decomposition
B. Rolling Wave Planning
C. Expert judgment
D. Deconstruction