PMP Exam Set G – Q56

As part of a strategy to handle negative risk, a project manager decided to adopt less complex processes, conduct more tests and choose a more stable supplier. What strategy would this be classified as?

A. Acceptance
B. Transference
C. Mitigation
D. Avoidance

C. Mitigation

PMP Exam Set G – Q43

All of the following activities are performed in the Close Project or Phase process EXCEPT

A. Activities that fulfill the exit criteria of the project
B. Sending the deliverables to the customer for acceptance
C. Activities which are needed to transfer the completed products to operations
D. Documenting the reasons for projects terminated early

B. Sending the deliverables to the customer for acceptance