PMP Exam Set G – Q56

As part of a strategy to handle negative risk, a project manager decided to adopt less complex processes, conduct more tests and choose a more stable supplier. What strategy would this be classified as?

A. Acceptance
B. Transference
C. Mitigation
D. Avoidance

C. Mitigation

PMP Exam Set D – Q98

Negative risks can either be ___________ , transferred, or mitigated as a countermeasure.

A. enhanced
B. avoided
C. exploited
D. ignored

B. avoided

PMP Exam Set D – Q87

Which of the following is not an appropriate method for dealing with a negative risk?

A. Avoid
B. Exploit
C. Transfer
D. Mitigate

B. Exploit