PMP Exam Set D – Q4

If you are working on a project where there is no definite project detailed scope, but similar projects have been completed in the past, what is the correct Estimate Activity Durations tool to use?

A. Analogous Estimating
B. Parametric Estimating
C. Critical Path Estimation
D. Three Point Estimating

A. Analogous Estimating
Tagged with 
Analogous Estimating Critical Path Estimation parametric estimating Three Point Estimating
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Info
  • PMP Exam Useful Formulas
Copyright © 2021 Premium PMP Exam Questions
×Close