A project manager is looking at a make-or-buy analysis as part of the Plan Procurement Management process. What type of costs should the project manager consider for this analysis?

A. Direct costs
B. Indirect costs
C. Out-of-pocket costs
D. Both direct as well as indirect costs

D. Both direct as well as indirect costs