PMP Exam Set G – Q86

A project manager is looking at a make-or-buy analysis as part of the Plan Procurement Management process. What type of costs should the project manager consider for this analysis?

A. Direct costs
B. Indirect costs
C. Out-of-pocket costs
D. Both direct as well as indirect costs

D. Both direct as well as indirect costs

PMP Exam Set F – Q60

The Make-or-Buy analysis is a technique that is used as part of the Plan Procurement Management process. It is used to determine whether a particular product or service can be produced by the project team or should it be purchased. The analysis to arrive at a decision should include:

A. Indirect costs only
B. Direct as well as Indirect costs
C. Direct costs only
D. Staffing costs only

B. Direct as well as Indirect costs