PMP Exam Set C – Q1

A project manager presented Earned value analysis data in a tabular format while providing a performance report. An alternative way in which the project manager could have presented the Earned value analysis data is by using:

A. A linear graph
B. An S-curve
C. A logarithmic curve
D. An Epsilon graph

B. An S-curve
Tagged with 
Earned value analysis Epsilon graph linear graph logarithmic curve Project Cost Management S-curve
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2026 Premium PMP Exam Questions
×Close