PMP Exam Set G – Q9 ( PMBOK 6th edition )

While analyzing the risks in a project, a project manager came up with a Risk Urgency Assessment document. In which process would this be done?

A. Close Risks
B. Monitor Risks
C. Perform Qualitative Risk Analysis
D. Plan Risk Management

C. Perform Qualitative Risk Analysis
Tagged with 
Control Risks Monitor Risks Perform Qualitative Risk Analysis Plan Risk Management Risk Urgency Assessment document
 

PMP Exam Set C – Q93

Which of the following processes produces a Risk Register?

A. Perform Quantitative Risk Analysis
B. Plan Risk Management
C. Perform Qualitative Risk Analysis
D. Identify Risks

D. Identify Risks
Tagged with 
Plan Risk Management Qualitative Risk Analysis Quantitative risk analysis risk register
 
Testimonials
"I have passed my PMP exam! Really appreciate for this free resources. Practicing PMP questions on my mobile is so easy with this site."
— Kamal Shankar (India), Team Lead

"I found the PMP questions very realistic; I'm glad I found this site!"
— William Scott (Canada), Project Manager

"Thank you for the PMP questions and PMP formulas. Very useful for my exam preparation."
— Aaron Cranston (USA), SAP Consultant

"I am so happy I discover this website! Day one and I can't believe how much I have learned already. Thank you."
— Zico Farias (Brazil), IT Manager


We appreciate testimonials as well as any feedback from you. Please contact us here.
  • PMP Exam Useful Formulas
Copyright © 2025 Premium PMP Exam Questions
×Close