PMP Exam Set A – Q100

A project is contracted as a Cost-Plus-Fixed-Fee (CPFF) type of contract with a fee of 10% of estimated costs. The estimated cost is US$ 50,000. If the project comes in at US$ 75,000 with no changes in project scope, what would be the total cost of the contract?

A. US$ 55,000
B. US$ 125,000
C. US$ 75,000
D. US$ 80,000

D. US$ 80,000

PMP Exam Set A – Q73

A project is contracted as a Time & Material (T&M) type of contract. The service provider initially estimates that the total effort involved would be about 1000 hours of effort. The project is contracted at a rate of US$ 75 per hour of effort. If the project ended up with 1200 hours of effort, what would the contract payout be.

A. US$ 75,000
B. US$ 90,000
C. US$ 82,500
D. US$ 120,000

B. US$ 90,000

PMP Exam Set A – Q65

A large network hardware upgrade project was scheduled to take place over a weekend. During the course of the implementation, several previously unidentified dependencies for additional materials were discovered. The project manager gave approval for the tech staff doing the implementation procure with corporate credit cards several hundred dollars worth of additional equipment required to complete the implementation. However these additional expenses caused the project to exceed its budget. How should the project manager handle this?

A. Ask the IT Director to cover those expenses from his budget.
B. Advise the staff to submit expense reports for the purchases. Because the cost is relatively small, it can be categorized as miscellaneous purchases that are not associated with the project.
C. Notify the project stakeholders immediately of the additional expenses incurred and follow project and or company procedures for budget variances.
D. Do nothing- that’s what reserves are for.

C. Notify the project stakeholders immediately of the additional expenses incurred and follow project and or company procedures for budget variances.

PMP Exam Set A – Q49

The costs on a project are typically classified as direct and indirect costs. The cost of electric utilities for the office would be considered as:

A. An indirect cost
B. Appraisal cost
C. A specific cost
D. A direct cost

A. An indirect cost

PMP Exam Set A – Q47

You are the Project Manager for KT’s Lumber Yard. You are trying to forecast estimates for the last phase of the project you are currently working on. Based on the performance of the project to date, which formula can be used to estimate the total value of the project when completed assuming similar variances will not occur?

A. ETC = (BAC – EV)/CPI
B. SV = EV – PV
C. CPI = EV/AC
D. EAC = AC + BAC – EV

D. EAC = AC + BAC – EV

PMP Exam Set A – Q11

Bill is the project manager of a software project that is originally estimated to complete in 12 months. 2 months into the project, it is discovered that the original estimating assumptions were fundamentally flawed. The Estimate at Completion (EAC) in such a project will be:

A. EAC = AC + Bottom-up ETC
B. EAC = BAC/CPI
C. EAC = AC + [BAC – EV]/CPI
D. EAC = AC + BAC – EV

A. EAC = AC + Bottom-up ETC