PMP Exam Set A – Q11

Bill is the project manager of a software project that is originally estimated to complete in 12 months. 2 months into the project, it is discovered that the original estimating assumptions were fundamentally flawed. The Estimate at Completion (EAC) in such a project will be:

A. EAC = AC + Bottom-up ETC
B. EAC = BAC/CPI
C. EAC = AC + [BAC – EV]/CPI
D. EAC = AC + BAC – EV

A. EAC = AC + Bottom-up ETC

PMP Exam Set A – Q10

Set A Q10

What is the shortest time possible to complete this project? (critical path)

A. 17 days
B. 18 days
C. 20 days
D. 22 days

B. 18 days

PMP Exam Set A – Q9

You have overheard two functional managers arguing about the impacts that your project will have on their departments. What is your best response?

A. Do nothing.
B. Analyze and report to each manager the impact your project will have on their departments in terms of time and resources required, and the relative enterprise priority of your project.
C. Inform the managers that the project sponsors had already considered this impact when they decided to implement the project.
D. Put in advance requests for resources from each department.

B. Analyze and report to each manager the impact your project will have on their departments in terms of time and resources required, and the relative enterprise priority of your project.

PMP Exam Set A – Q7

Which process group corresponds to the “act” component of the plan-do-check-act cycle?

A. Executing
B. Monitoring and Controlling
C. Planning
D. Initiating

B. Monitoring and Controlling

PMP Exam Set A – Q4

You are managing a project to design microprocessor control systems. The design work was estimated to complete in 3.5 months, with seven milestones. The sixth milestone is the prototype to be handed over to manufacturing. All milestones before prototyping have been completed ahead of schedule with 6th one being delayed for 4 months as the prototype has been sent back several times, due to conflicts between departments. You are now planning to hold a meeting to review the design specifications, and handle conflicts between design and manufacturing. Who is at fault?

A. The scheduler.
B. The project manager.
C. The manufacturer.
D. The design engineer.

B. The project manager.

PMP Exam Set A – Q2

Your manager has asked you to include the Human Resource Management Plan and the Schedule Management Plan in your Project Management Plan. Is this the appropriate place for these items?

A. No, these are stand alone documents only.
B. Yes, you should unquestioningly include anything your manager suggests.
C. No, these documents should not be created until later in the project.
D. Yes, include them in the Project Management Plan.

D. Yes, include them in the Project Management Plan.