You work at a software company that authors Material Safety Data Sheets (MSDS) for chemical companies. Prior to releasing the MSDS to the company you have created a list of items to be reviewed to see that they appear on the document such as: chemical name, CAS#, protection required, what to do an emergency, etc.

PMP Exam Set D – Q71

Three strategies that typically deal with negative risks or threats are: A. Enhance, Share and AcceptB. Transfer, Exploit and AcceptC. Avoid, Transfer and ExploitD. Avoid, Transfer and Mitigate Show Answer D. Avoid, Transfer and Mitigate

PMP Exam Set D – Q70

Which of these is not an approved Estimate Activity Durations technique? A. Three Point EstimatingB. Parametric EstimatingC. Analogous EstimatingD. Critical Path Estimation Show Answer D. Critical Path Estimation

PMP Exam Set D – Q69 ( PMBOK 6th edition )

A project manager has scheduled technical training for her project team members in order to increase their skills. During which of the following processes these trainings will be delivered to the team members? A. Manage QualityB. Acquire ResourcesC. Develop TeamD. Plan Resource Management Show Answer C. Develop Team

PMP Exam Set D – Q68

There are 10 stakeholders in MegaMart’s ERP deployment project. How many potential communications channels are there? A. 25B. 10C. 45D. 30 Show Answer C. 45

PMP Exam Set D – Q67

A large construction project for a logistics company will require the expenditure of a large amount of capital. The finance group works with the project manager to project set limits when expenses will be incurred in a given project, and determine if there are ways to smooth out or level the spending to avoid a

PMP Exam Set D – Q66

You are managing a project that has a task to translate several pages of a document into Spanish. This is very similar to a project done last year where a document was translated into German. You are not sure how long it will take to translate into Spanish so you look at the project plan

PMP Exam Set D – Q65

Which of the following is not a Risk-Diagramming Technique? A. Influence diagramsB. Control chartsC. Cause-and-Effect diagramsD. System flowcharts Show Answer B. Control charts

PMP Exam Set D – Q64

During your weekly status reports you are reporting the earned value for the project. This information is important for you and the stakeholders to gauge the progress of the project. What process group are the cost and schedule control part of? A. ClosingB. PlanningC. ExecutingD. Monitoring and Controlling Show Answer D. Monitoring and Controlling

PMP Exam Set D – Q63

A project manager of a project that was contracted on a Time and Material basis finds that some of the tasks have been taking lesser time than planned. On average each team member has required only 30 hours to accomplish work which was planned for 40 hours during the week. The project manager should: A.