Two efficiency indicators that reflect the cost and schedule performance of a project are: A. Cost Projection Index (CPI) and Schedule Projection Index (SPI)B. Cost Performance Index (CPI) and Schedule Performance Index (SPI)C. Actual Cost (AC) and Planned Value (PV)D. Cost Pricing Index (CPI) and Schedule Performance Index (SPI) Show Answer B. Cost Performance Index
PMP Exam Set D – Q91 ( PMBOK 6th edition )
Peter is the project manager of an external project for a customer. The project is expected to take about a year to complete. Six months into the project, the customer informs Peter that the project needs to be scrapped. During which of the following processes would procedures be developed to handle early termination of a
PMP Exam Set D – Q90
Jane is currently populating her project’s stakeholder register with the names and details of the people identified during the Identify Stakeholders process. Some of these people are not supporting the project but they can directly influence the project. Jane is adding these people to her project’s stakeholder register because? A. These people are negative stakeholders
PMP Exam Set D – Q89
Which of the following is not accurate about the initial phase of a project? A. The highest uncertainty is at this stage of the projectB. The cost associated at the beginning of the project is highestC. Stakeholders have maximum influence during this phaseD. Staffing levels are the highest at this stage Show Answer B. The
PMP Exam Set D – Q88
Which of the following is not an enterprise environmental factor influencing the Develop Project Management Plan process? A. Project management body of knowledgeB. Governmental or industry standardsC. Project Management Plan templateD. Project management information system Show Answer C. Project Management Plan template
PMP Exam Set D – Q87
Which of the following is not an appropriate method for dealing with a negative risk? A. AvoidB. ExploitC. TransferD. Mitigate Show Answer B. Exploit
PMP Exam Set D – Q86
Variance analysis refers to cost performance measurements used to assess the magnitude of variation in comparison to the original cost baseline. What is the trend on the percentage range of acceptable variances as the project progresses? A. The percentage range of acceptable variances will tend to decrease as the project progresses.B. The percentage range of
PMP Exam Set D – Q85
Which of the following is not an example of parametric estimating? A. Activity duration estimated based on the number of drawings multiplied by the number of labor hours per drawing.B. Activity duration estimated based on the number of labor hours per meter for cable installation.C. Activity duration estimated based on the square footage in construction.D.
PMP Exam Set D – Q84 ( PMBOK 6th edition )
A project manager is planning out the availability of resources as part of the Acquire Resources process. He needs to acquire resources that report to a functional manager. What technique will he likely use to obtain these resources? A. Pre-assignmentB. AuthorityC. NegotiationD. Coercion Show Answer C. Negotiation
PMP Exam Set D – Q83
In the procurement process, the seller may be viewed initially as a bidder, then as the selected source and then as the contracted supplier. The seller will typically manage the work as a project. In such an instance, which of the following is not true? A. The Buyer becomes the customer and is thus a