PMP Exam Set B – Q51

When a negative unidentified risk occurs in a project, a response to it would be called: A. Disaster recoveryB. Failure planningC. A workaroundD. Backup planning Show Answer C. A workaround

PMP Exam Set B – Q50

It was found that there were a large number of hidden requirements to be uncovered in the Collect Requirements phase. Which of the following tools should a project manager use to identify them? A. Participant observerB. QuestionnairesC. SurveysD. Interviewing Show Answer A. Participant observer

PMP Exam Set B – Q49

A project manager is confused about the perspective of the buyer-seller relationship in the context of project procurement management. How would your clarify this? A. The buyer-seller relationship exists only between organizations external to the acquiring organization.B. The buyer-seller relationship exists only between organizations internal to the acquiring organization.C. The buyer-seller relationship is applicable only

PMP Exam Set B – Q48

The Actual Cost (AC) is the total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure component. What is the upper limit for the AC? A. 50% over and above the Planned Value (PV)B. The Actual Cost (AC) is limited to the Planned Value (PV).C. 100% over and

PMP Exam Set B – Q47

As part of the procurement process, the procuring organization elected to have an estimate of costs prepared by an outside professional estimator. The estimator came up with an estimate of $ 500,000. However, the cost estimates prepared by prospective sellers were in the range of $ 200,000. How can this be best interpreted? A. The

PMP Exam Set B – Q46

A change request has just been formally documented and approved by the Change Control Board. The project manager now needs to communicate this to a project team member. Which of the following activities must the project manager necessarily do? A. Telephone the team member and inform him/her about the changes.B. Plan for a meeting over

PMP Exam Set B – Q45

The change requests created as an output of the Monitor and Control Project Work process may be attributed to all of the following except: A. Preventive ActionB. Defect RepairC. Project status updateD. Corrective Action Show Answer C. Project status update

PMP Exam Set B – Q44

If you want to compress a project schedule, what are two of the recommended alternatives to consider? A. Fast Tracking and Schedule Network AnalysisB. Crashing and Fast TrackingC. Resource Leveling and What-If Scenario AnalysisD. Crashing and Schedule Network Analysis Show Answer B. Crashing and Fast Tracking

PMP Exam Set B – Q43

Andrew is managing a construction project. He is using his communication, interpersonal and management skills to keep the key project stakeholders engaged with the project. Which of the following activities is not related to the Manage Stakeholder Engagement process? A. Addressing and resolving issuesB. Adjusting the stakeholder management strategyC. Confirming the stakeholders’ continued commitmentD. Negotiating