PMP Exam Set B – Q72

You are a Project Manager and are nearing the end of your project. You are now required to provide lessons learned documentation on the project. What is the MAIN purpose for preparing lessons learned documentation? A. To identify the valued employees who improved efficienciesB. To identify the problem employees who reduced efficienciesC. To identify instances

PMP Exam Set B – Q71

The key components of the basic model of communication between two parties are: A. Encode, message, medium, noise, decodeB. Encode, send, receive, replicate, replyC. Encode, send, receive, distribute, respondD. Encode, send, interference, decipher, acknowledgment Show Answer A. Encode, message, medium, noise, decode

PMP Exam Set B – Q70

Peter, a project manager, is updating the status of his project. Based on the performance indices, he expects the project to finish a month earlier than the planned finish date. However, he expects the project to exceed the budgeted costs. What can you say about the schedule performance index (SPI) of the project? A. The

PMP Exam Set B – Q69

Which of the following methods of forecasting EAC and ETC is the most accurate? A. ETC based on CPIB. ETC based on BACC. ETC based on CPI and SPID. ETC based on new estimate Show Answer D. ETC based on new estimate

PMP Exam Set B – Q67

Which of the following roles in a project is more likely to be involved in negotiations on procurements during the Conduct Procurements phase? A. Procurement administratorB. Project coordinatorC. Project managerD. Project sponsor Show Answer A. Procurement administrator

PMP Exam Set B – Q66

You have taken over the management of a project from another project manager, who is a certified PMP. This project has been completed and is in the process of closing. You discover that there is no project schedule. What do you do? A. Add this issue to the lessons learned database.B. Do nothing.C. Notify the

PMP Exam Set B – Q65

You have been managing a National freeway construction project which is intended to improve the transportation between east and west regions of a country. Being in the execution phase, the change control board has approved many change requests generated from stakeholders including the freeway transportation agency. At least half of those requests were made to

PMP Exam Set B – Q64

While managing a large project, the project manager decided to include indirect costs as part of his cost estimate. If indirect costs are included in an estimate which of the following is true? A. Indirect costs should be included at the activity level or higher levels.B. Indirect costs must be included at the activity level