PMP Exam Set B – Q42

The Direct and Manage Project Work process has three tools and techniques. Two of them are Expert Judgment and Meetings. What is the third one? A. Scheduling SystemB. Configuration Management SystemC. Project Management Information SystemD. Change Control System Show Answer C. Project Management Information System

PMP Exam Set B – Q41

Your company is way behind schedule in the deployment of a government mandated change to a health care processing system that must be in production by the end of the year. You and your team have met and decided to hire an additional 50 programmers to work with the existing staff on the activities in

PMP Exam Set B – Q40

Which of the following statements about project teams is incorrect? A. The project management team is usually a team external to the project team.B. The project management team is a subset of the project team.C. For smaller projects, the project management responsibilities can be shared by the entire team.D. For smaller projects, the project management

PMP Exam Set B – Q39

A project manager is giving a project update to the key stakeholders. During the meeting, he finds out that most of the stakeholders are busy checking and replying to their emails. Which of the following is the best action that could have eliminated this issue? A. A meeting ground rule on active listeningB. Providing snacks

PMP Exam Set B – Q38

You have just learned that your project’s sole equipment supplier has gone out of business. This is an unanticipated risk, and will cause a delay in the project until a new vendor can be selected and contracts put in place. What do you do? A. Continue working on non critical path tasks.B. Put out on

PMP Exam Set B – Q36

A seller organization was executing work for a project under a contract. During the course of the project, a number of disputes arose over the scope and quality of work. Which of the following is the preferred method of resolving these claims? A. Alternative dispute resolution (ADR)B. Claims courtC. Appeals courtD. Negotiation Show Answer D.

PMP Exam Set B – Q35

A project manager was involved in preparation of the project charter for an external project. One of the inputs to the project charter was a statement of work (SOW). The SOW may have been received from the customer as part of all of the following except: A. As part of a request for informationB. As