Peter is managing a software development project. The buyer of the product is an external entity. During the execution of the project, Peter finds out that a new operations manager has been hired in the customer organization. The new manager is now a key stakeholder of the project. Which of the following documents is least likely to get updated as a result of the addition of this new stakeholder?
A. Stakeholder register
B. Risk register
C. Stakeholder management plan
D. Issue log