PMP Exam Set E – Q52

You are the Project Manager for the production of an exotic car. You have completed the Define Scope process for your project. Which of the following may be generated through this process?

A. Project scope statement, Project charter
B. Project scope statement, Updates to Requirements traceability matrix
C. WBS, Updates to Requirements traceability matrix
D. Project scope statement, WBS

B. Project scope statement, Updates to Requirements traceability matrix

PMP Exam Set B – Q55

You are the Project Manager for GeoThermal Systems. Which of the following must be done FIRST before proceeding with a new project?

A. Create the Project Scope Statement
B. Stakeholder analysis
C. Product analysis
D. Obtain Project Charter approval

D. Obtain Project Charter approval