Jane is managing an office refurbishment project. All of the project stakeholders have been identified and classified. The stakeholder management plan has also been approved. Jane is managing a project for the first time in her life and she is relying on the PMBOK guide as a reference to deliver a great project.
Which of the following processes would provide guidance to Jane regarding how to execute the approved stakeholder management plan?
A. Monitor Stakeholder Engagement
B. Manage Stakeholder Engagement
C. Identify Stakeholders
D. Plan Stakeholder Engagement