As part of risk planning, some responses are designed for use only if certain events occur. A project manager of a multi-year project decided to trigger one such set of responses during the Monitor Risks process. Which of the following is likely to have triggered the responses? A. Late receipt of status reportsB. A key
PMP Exam Set F – Q81
A Responsibility Assignment Matrix illustrates the connections between the work that needs to be done and the project team members. A RACI chart is a type of Responsibility Assignment matrix where the names of the roles being documented are: A. Responsible, Administration, Check and InformB. Reportable, Actionable, Check and InformC. Responsible, Accountable, Consult and InformD.
PMP Exam Set F – Q80
You are managing a project to manufacture widgets for a customer. The customer has come to the factory to examine the product, and determines that while the product itself meets its requirements, the manner in which about half the widgets have been packaged does not meet requirements and is insisting they be repackaged. This re-work
PMP Exam Set F – Q79
The Identify Risks process involves determining which risks may impact a project. It is considered an iterative process. What is the frequency of the iteration? A. Every monthB. Every fortnightC. The frequency of iteration will vary based on the situationD. Every week Show Answer C. The frequency of iteration will vary based on the situation
PMP Exam Set F – Q78
Colocation is also referred to as: A. Strong matrixB. Weak matrixC. Tight matrixD. Balance matrix Show Answer C. Tight matrix
PMP Exam Set F – Q77
As the project manager of a high-visibility project, you are in the process of Identifying risks. You are concerned that the data you collect might be biased. A technique that helps keep the bias out of the data and keeps any one person from having undue influence on the outcome is: A. InterviewingB. Round-robin techniqueC.
PMP Exam Set F – Q76
A project manager is performing Reserve Analysis as a technique in one of the project management process that he is currently working on. Which of these is likely to be that process? A. Estimate ReservesB. Report CostsC. Estimate CostsD. Plan Costs Show Answer C. Estimate Costs
PMP Exam Set F – Q75
A project charter that formally authorized a project was created. The project charter documented the initial requirements to satisfy stakeholders’ needs and expectations. How often should the project charter ideally be revised? A. At the beginning, middle and end of a project.B. Once a monthC. NeverD. As required by the PMO. Show Answer C. Never
PMP Exam Set F – Q74
A Work Breakdown Structure is a hierarchical illustration of all the work to be done in a project. A WBS component does not represent: A. productsB. resultsC. servicesD. project activities Show Answer D. project activities
PMP Exam Set F – Q73
The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives. This is created as part of: A. Project Integration ManagementB. Project Scope ManagementC. Project Procurement ManagementD. Project Schedule Management Show Answer B. Project Scope Management