Which process is MOST responsible for managing changes to the schedule components of the Project Management Plan? A. Control ScheduleB. Create WBSC. Develop Project Management PlanD. Develop Schedule Show Answer A. Control Schedule
PMP Exam Set F – Q41
Jane is managing a multi-million dollar shopping complex construction project. The buyer of the project is an external entity. After identifying all the key and major project stakeholders, Jane is now planning to carry out a comprehensive stakeholder analysis. Which of the following is not involved with the stakeholder analysis? A. Identifying potential stakeholdersB. Identifying
PMP Exam Set F – Q40
If you are requesting a vendor quote for a defined scope, what is the recommended contract type? A. Fixed priceB. CommissionC. Cost reimbursableD. Time and materials Show Answer A. Fixed price
PMP Exam Set F – Q39
Which of these statement correctly links project and product life cycles? A. A product life cycle is generally contained within a project life cycle.B. A project life cycle is generally contained within a product life cycle.C. A product life cycle is the same as a project life cycle.D. The last life cycle for a project
PMP Exam Set F – Q38
The WBS represents all product and project work. The total work at the lowest levels should roll up to the higher levels so that nothing is left out and no extra work is performed. This is also called as: A. 100% ruleB. 80/20 ruleC. Pareto’s ruleD. Ground rule Show Answer A. 100% rule
PMP Exam Set F – Q37
A project manager is about to start on a new project. Where would he find details about his authority level in the project? A. Organizational Process AssetsB. The Project CharterC. The PMBOKD. The Scope statement Show Answer B. The Project Charter
PMP Exam Set F – Q36
A very critical resource is on another project team. It is very important you get his time for your project. You have contacted his team’s manager multiple times, but have received a poor response. What should you consider doing next? A. Plan for an alternate resource since this resource is not available.B. Try to use
PMP Exam Set F – Q35
You’ve just completed a solid waste management project in an under-developed country. The contractor you are working for has a strict policy of abiding by local laws and rules, although the local resources working on the project have a much more lax approach to following laws and policies. Now at the end of the project,
PMP Exam Set F – Q34
Which of the following is not an example of data that may be presented in a performance report? A. Earned valueB. Quality metricsC. Schedule varianceD. Project charter Show Answer D. Project charter
PMP Exam Set F – Q33
You have been called in to give an executive presentation on the status of your project. Just before you walk into the meeting, you are informed that a critical resource for the project is no longer available, and could result in a substantial delay to the project. However, you believe there may be an alternative