Your company took over the management of a project from another company that went out of business. To minimize disruptions related to the transition, your company hired a number of the employees from the other company. One of these employees has delivered a 300 page document a week ahead of schedule. However, while walking past
PMP Exam Set E – Q71
Andrew is the project manager of a project and is planning responses to a set of risks. As a direct response of implementing this risk response, he anticipates certain other risks to arise. These would be termed as: A. Secondary risksB. Primary risksC. Planned risksD. Workaround Show Answer A. Secondary risks
PMP Exam Set E – Q70
A first-time project manager is advised by an experienced project manager that he needs to plan for cost of quality. The first-time project manager is not sure of what costs are included in the cost of quality. What would your advise be? A. Cost of quality only includes cost of nonconformanceB. Cost of quality includes
PMP Exam Set E – Q69
You have just been hired by a waste management company to start a solid waste management program in an under-developed country. The project will be on a build-operate-transfer basis and have a duration of 2 years. At close of the project, the program will be run by local authorities. The project has been sponsored by
PMP Exam Set E – Q68 ( PMBOK 6th edition )
Which of the following is the process of communicating and working with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholder engagement? A. Manage Stakeholder EngagementB. Monitor Stakeholder EngagementC. Manage CommunicationsD. Monitor Communications Show Answer A. Manage Stakeholder Engagement
PMP Exam Set E – Q67
In a project that was yet to begin, many of the project team members were known in advance. This is called: A. Proactive-planningB. Skill-matchingC. Pre-assignmentD. Staffing-assignment Show Answer C. Pre-assignment
PMP Exam Set E – Q66
Emily is the project manager for a dam construction project. All project communications are recorded and documented for future reference. It has been decided that the project team will maintain last three months of project communication records at any given point in time. It has also been decided that the older communication records will be
PMP Exam Set E – Q65
Which of the following roles in a project is more likely to be involved in negotiations on procurements during the Conduct Procurements phase? A. Procurement administratorB. Project coordinatorC. Project managerD. Project sponsor Show Answer A. Procurement administrator
PMP Exam Set E – Q64
Which of the following should be done FIRST during the Project Life Cycle? A. List the key people and organizations that have a stake in the project.B. Ascertain the stakeholder interests and expectations for the project.C. Identify the key people and organizations that have a stake in the project.D. Select and quantify the stakeholder interests
PMP Exam Set E – Q63
The method used in the plan quality management process to identify the factors that may influence specific variables of a product under development is known as: A. The forecasting techniqueB. The control chartC. The statistical samplingD. The design of experiments Show Answer D. The design of experiments