PMP Exam Set E – Q52

You are the Project Manager for the production of an exotic car. You have completed the Define Scope process for your project. Which of the following may be generated through this process? A. Project scope statement, Project charterB. Project scope statement, Updates to Requirements traceability matrixC. WBS, Updates to Requirements traceability matrixD. Project scope statement,

PMP Exam Set E – Q51

The Actual Cost (AC) is the total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure component. What is the upper limit for the AC? A. 50% over and above the Planned Value (PV)B. The Actual Cost (AC) is limited to the Planned Value (PV).C. 100% over and

PMP Exam Set E – Q50

You have just taken over a project from another project manager about 6 months into a 12-month project. As you get to know the staff on the project, you become aware that 5 staff members are relatives of the previous project manager. What do you do? A. Notify your project stakeholders there is a possibility

PMP Exam Set E – Q49

You have been assigned as a project manager of a new project to be executed out of New York. However, you determine that the project requires a Global Positioning Systems Expert who is not available within the company in New York. On doing a little checking, you determine that the company has an expert based

PMP Exam Set E – Q47

Peter is managing a website development project. He has recently received a feedback from one of the key project stakeholders. The feedback is overall positive but it contains some recommendations. After analyzing the recommendations, Peter accepts them, gets them approved and incorporates them into the project management plan. What needs to be done with this

PMP Exam Set E – Q46

No matter how good you are in communicating, information distribution to stakeholders as planned is a challenging task. Many tools and techniques are used during the Manage Communications process EXCEPT: A. Performance reportingB. Work performance reportsC. Communication technologiesD. Communication models Show Answer B. Work performance reports

PMP Exam Set E – Q45

A project manager is using a Risk Diagramming technique that is a graphical representation of situations showing causal influences, time ordering of events and other relationships among variables and outcomes. This would be: A. A System flow chartB. An Influence DiagramC. Pareto chartD. Risk flow diagram Show Answer B. An Influence Diagram

PMP Exam Set E – Q44

While managing a project, you decide to contract to an external enterprise. You enter into a contract where you pay the external enterprise a set amount (as defined by the contract), irrespective of the seller’s costs. What would best describe this type of contract? A. FP-EPAB. FFPC. FPIFD. CPFF Show Answer B. FFP

PMP Exam Set E – Q43

Which of the following processes deals with maintaining the integrity of baselines by releasing only approved changes for incorporation into the project management plan? A. Perform Integrated Change ControlB. Direct and Manage Project WorkC. Develop Project Management PlanD. Monitor and Control Project Work Show Answer A. Perform Integrated Change Control