The organization’s safety and health policy, ethics policy, project policy, and quality policy can be used in a project to influence it’s success. All these policies are a part of: A. Organizational process assetsB. The project management planC. Enterprise environmental factorsD. Historical databases Show Answer A. Organizational process assets
PMP Exam Set E – Q31
A planning technique used to provide products, services and results that truly reflect customer requirements by translating those customer requirements into the appropriate technical requirements for each phase of project product development is called: A. Six SigmaB. PDCAC. Voice of the CustomerD. ISO Show Answer C. Voice of the Customer
PMP Exam Set E – Q30
A project manager from a buyer organization is invited to lunch by the manager of a seller organization. The project manager’s organization does not permit receipt of gifts from vendors. The project manager should: A. Go out for lunch and refrain from informing his / her managers about the lunch.B. Avoid going out to lunch
PMP Exam Set E – Q29
Sally, a project manager was reconciling expenditure of funds with funding limits on the commitment of funds for the project. She found a large variance between the funding limits and planned expenditures. As a result, she decided to reschedule work to level out the rate of expenditures. This is known as: A. Funding limit reconciliationB.
PMP Exam Set E – Q28 ( PMBOK 6th edition )
Which of the following is NOT a tool or technique of the Acquire Resources process? A. NegotiationB. Multi-criteria decision analysisC. Pre-assignmentD. Conflict management Show Answer D. Conflict management
PMP Exam Set E – Q27
A number of deliverables were submitted to the buyer as part of a project. Where would the project manager find documentation on the requirements for formal deliverable acceptance and how non-conforming deliverables can be addressed? A. In the SOWB. In the lessons learned documentC. In the deliverable release note.D. In the agreement Show Answer D.
PMP Exam Set E – Q26
The Executive VP of Finance has informed you that you will be the Project Manager for an energy audit the company is performing in order to save expenses. He has tasked you to identify the stakeholders and to start documenting the high-level assumptions and constraints. Your project is in what stage? A. InitiatingB. PlanningC. Monitoring
PMP Exam Set E – Q25
You are the project manager responsible for building a 100,000 sq. ft. data center. One of the schedule activities in your plan is to install the Computer Room Air Conditioning (CRAC) units, however in order to start the installation of the units the raised floor in the data center must be completely installed first. This
PMP Exam Set E – Q24
Accounting for the limited resources in the project schedule is called: A. Forward passB. Critical chain methodC. Backward PassD. Critical Path Method Show Answer B. Critical chain method
PMP Exam Set E – Q23
When writing the roles and responsibilities for team members, you should document the role, authority, responsibility and competency for each team member. Where must this information be documented? A. Human resource management planB. RACI chartC. Resource calendarD. Resource Breakdown Structure (RBS) Show Answer A. Human resource management plan